Improvements included installing exclusive left turn lanes on Bliss Road and Wheeler Road and an exclusive right turn lane on the southbound portion of Illinois Route 47, resurfacing, traffic signal modifications, sidewalk and bike path installation, drainage improvements, grading, and landscaping.
Highlights
$1,540,000 Federal Funds
2014-2020
- Phase I, II and III Engineering Services
- Location Drainage Study
- Capacity Analysis and Intersection Design Study (IDS)
- Geometric Study with Crash Analysis
- HMA Pavement Reconstruction and Widening
- PCC Sidewalk
- Traffic Signal and Interconnection Modifications
- HMA Shared-Use Path
- Weekly Progress Meetings
- ICORS/CMMS Documentation
- Coordination with IDOT, KDOT, and Village Staff