EEI provided design and construction engineering services for a new Iron-Galesville Deep Sandstone Well with a target capacity of 1,000 GPM. The project consisted of well analysis, analysis of well aquifer capacity and pumping hydraulics, bidding, permitting, and construction oversight. The associated cation exchange water treatment plant with hydrogen sulfide removal is currently under construction with completion scheduled in Summer 2025.

Highlights

Awarded Bid Amount: $1,470,800

Final Construction Cost: $1,199,600

2012-2023

  • Ironton-Galesville Deep Sandstone Well with Target Capacity of 1,000 GPM
  • Well Site Analysis
  • Analysis of Well Aquifer Capacity and Pumping Hydraulics
  • IEPA Construction Permitting
  • Bidding Coordination and Construction Oversight